- Date: Summer 2023
- Customer: MnDOT
- Project Type: Class 5 Rock & Washed Concrete Sand
Rock On
Dakota Aggregates produced and distributed approximately 226,700 tons of material for the 15 mile long HWY 52 project in Rosemount, MN in 2023. On average, each hauler holds 23 to 25 tons of material (rock or sand) per load, approximately 15 to 16 yards per load.
The project will improve drainage, provide a smoother road surface and extend the pavement life of the road. Ten of the fifteen miles are finished and the remainder is expected to be complete in the fall of 2024.